Eskom to defer the replacement of steam generators at Koeberg Unit two until August 2023

Published on


Add Smile FM on Google

Eskom says it has decided to defer the replacement of three steam generators at Koeberg Unit two until August 2023.

The power-utility said preliminary evaluations have shown that the replacement will have to be postponed to prevent possible load shedding in the winter months.

Chief Operating Officer at Eskom, Jan Oberholzer says Koeberg Unit 2 was disconnected from the national grid in January 2022.

Oberholzer says the unit would still be returned online by June this year.

Eskom says the postponement of the installation of the steam generators will not affect the safety of the power station.

Chief nuclear power officer at Eskom, Riedewaan Bakardien.

He says the unit will still be fully functional until the steam generators are replaced.

Access the full briefing here.

Related articles:

Latest articles

WATCH: Tatjana Smith switches to Netherlands after speaking out about Swimming SA

 South Africa’s most decorated Olympian, Tatjana Smith, has made an emotional announcement today, switching her sporting allegiance to the Netherlands after World Aquatics approved...

Still going strong! Western Cape seniors prove age is just a number

  Who says fun, fitness and a little friendly competition are only for the young? Ninety-two spirited seniors from across the Western Cape proved that...

Mitchells Plain motorists warned of temporary road closures

 Residents and motorists in Mitchells Plain are being advised to prepare for temporary road closures as resurfacing work gets underway in parts of the...